CM Naqvi Pushes for Completion of Band Road Project
Lahore: Punjab Care Taker Chief Minister (CM) Mohsin Naqvi actively pursues the completion of the “Controlled Access Corridor Band Road Project”. He has been taking notable steps to oversee the progress of the project.
Read more: LDA Building and Zoning Regulations-2019 to get Reforms
CM Naqvi carried out an inspection spanning over 8km of the area involving 55% of Package 2 (Babu Sabu to Sagian) and 74% of Package One (Sagian to Niazi Chowk). During his visit of the project, he also inspected the work on both projects and urged the team to ensure the negation of delays in the project.
Read more: RDA, LDA Discuss Record Digitalization
CM Naqvi also directed to expedite Package Two with the deployment of additional resources for early completion. With his clear-cut directives, the subordinate team ensured the CM for the work on the project to be completed by the first week of February with all the available resources. The projects are of utmost importance for addressing traffic issues in areas surrounding both the projects in Lahore.
For more information, please visit Fuldax Marketing.
We are 24/7 available.
Call us today 0300 5550291